MANCHESTER GRAND HYATT
Manchester Grand Hyatt San Diego, CA
Project Summary:
The extensive lobby and bar renovation included the addition of a large decorative screen located at the reception area, relocation of the lobby bar. The renovation opened the lobby and brightened up the area.
Key Project Stats:
- Approved budget: $10,314,000
- Final budget spent: $10,066,014
- 30,400 sq. foot renovation
- Includes 20,000 sq ft of tile floor removal and replacement
- Work completed during high season for group events.
- Developed multiple phased egress plans for safe egress during events (see attached floor plan)
- Developed multiple construction phase plans to facilitate timely completion.
- 1-year project duration
PHOENICIAN RESORT
Phoenician Resort Scottsdale, AZ
Project Summary:
The lobby renovation included the relocation of the lobby bar to have a grand view of the desert mountain landscape. The renovation took the 1980’s décor and brought light and life back to the resort.
Key Project Stats:
- Approved budget: $6,138,000
- Final budget spent: $5,825,500
- 32,520 sq. foot renovation
- 6-month project duration